The acute shortage of coal at thermal power plants in Punjab has forced power utility PSPCL to cut power generation and impose rotational load shedding at several places, attracting the state government to the Center for insufficient coal supply. Used to be. An official of Punjab State Power Corporation Limited said on Saturday that coal-fired power plants are running at low capacity due to shortage of coal.

An official of Punjab State Power Corporation Limited said that due to the critical power situation, coal reserves in the state are left with power plants for five days. “The plants are running at low capacity. He said that these are not being run at full capacity to conserve coal.

Punjab Chief Minister Charanjit Singh Channi on Saturday hit out at the Center for inadequate coal supply and feared closure of thermal power plants in the state in the next few days due to rapidly depleting coal supplies. He said that Punjab was not getting enough coal despite agreements with various subsidiaries of Coal India Limited and asked the central government to ensure that the state’s coal bidding is done immediately to tide over the power crisis.

The current power demand in the state is around 9,000 MW. Officials said that apart from the demand for electricity from the agriculture sector, the need for electricity in the state is also increasing due to higher temperature during the day.

Though PSPCL officials claimed minimum load shedding, there are reports of power cuts for two to three hours at many places in the state. Reviewing the power situation in the state amid short supply of coal, the Chief Minister said that due to insufficient coal availability, all thermal plants are not generating power at full capacity.

However, he reiterated his government’s firm commitment to provide electricity supply to irrigate the paddy crop, where it is required at the last mile of the crop’s yield. Channi, however, said in a statement that power cuts are being made on domestic consumers in cities and villages to ensure adequate supply to the agriculture sector as well as to maintain grid discipline.

PSPCL Chairman and Managing Director A Venu Prasad told Channi that thermal plants across the country are facing coal shortage and coal supply crisis. Within the state, independent power generation (IPP) plants Nabha Power Ltd (1.9 days), Talwandi Sabo Power Ltd (1.3 days) and GVK (0.6 days) have less than two days of coal left.

The state-owned Ropar Thermal Plant and Lehar Mohabbat Thermal Plant have coal stocks left for four and five days respectively, the official said. As per the guidelines of the Central Electricity Authority, power plants located at a distance of more than 1,000 km from a coal mine should always have a minimum coal stock of up to 30 days, but this level of stock is not maintained by the power plants. State.

On Friday, the power plants had received some coal supplies to run their operations, the official said. The official said that in view of the low generation of electricity, PSPCL is buying power through the power exchange, but its price is more than Rs 10 per unit, which is very expensive.

Venuprasad said that he has written a letter to the Center to increase the supply of coal to the state. Officials claimed that the situation is expected to return to normal in the next few days.

read all breaking news, breaking news And coronavirus news Here. follow us on Facebook, Twitter And wire.

.

RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Recent Comments